QUESTION 41

- (Topic 2)
Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?

Correct Answer: B

QUESTION 42

- (Topic 3)
Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme?

Correct Answer: B

QUESTION 43

- (Topic 3)
You are the program manager for the HNY Corporation and you complete programs for other companies in your role. You have just been assigned a new program that is very similar to a recently completed program you did for your company. Management has asked you to create a cost estimate for the program so you base your current cost estimate on the recently finished program. What type of estimating technique have you used in this instance?

Correct Answer: C

QUESTION 44

- (Topic 1)
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines
the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Correct Answer: C

QUESTION 45

- (Topic 2)
Which one of the following is not an output of the direct and manage program execution process?

Correct Answer: B