QUESTION 26

- (Topic 1)
In which of the following processes is the program charter created?

Correct Answer: C

QUESTION 27

- (Topic 3)
Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."

Correct Answer: C

QUESTION 28

- (Topic 3)
According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

Correct Answer: C

QUESTION 29

- (Topic 3)
If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?

Correct Answer: A

QUESTION 30

- (Topic 3)
Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?

Correct Answer: C