QUESTION 71

- (Topic 1)
You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must
review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

Correct Answer: B

QUESTION 72

- (Topic 1)
What is the formula to determine earned value (EV) for a program?

Correct Answer: C

QUESTION 73

- (Topic 2)
You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

Correct Answer: B

QUESTION 74

- (Topic 2)
You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

Correct Answer: B

QUESTION 75

- (Topic 2)
You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

Correct Answer: D