QUESTION 56

- (Topic 2)
You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Correct Answer: C

QUESTION 57

- (Topic 1)
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Correct Answer: C

QUESTION 58

- (Topic 4)
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Correct Answer: A

QUESTION 59

- (Topic 3)
You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

Correct Answer: A

QUESTION 60

- (Topic 3)
Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Correct Answer: C