QUESTION 46

- (Topic 3)
Which of the following documents describes the details for each component in the WBS?

Correct Answer: C

QUESTION 47

- (Topic 3)
You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Correct Answer: C

QUESTION 48

- (Topic 3)
Communication is large percentage of program execution as the program manager must communicate with the appropriate stakeholders. In larger programs face-to-face communication is not always possible. When emails are used what verbal aspect of communication is lost?

Correct Answer: D

QUESTION 49

- (Topic 2)
You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Correct Answer: A

QUESTION 50

- (Topic 3)
What does CPI value less than 1.0 indicates?