You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team handle this strategic change. Which of the following can serve as input here?
Correct Answer:
D
Your team members were having a discussion about the contents of the Portfolio Charter and they came to you for advice because they could not agree on a common answer. What would be your advice to them?
Correct Answer:
B
The portfolio management information system is often a collection of spreadsheets rather than automated tools. An effective PMIS enables the portfolio manager to define, analyze, design, produce, and manage information systems to support a successful portfolio, and includes tools and processes such as:
Correct Answer:
D
A number of components proposals are on the table as a result of the strategic planning cycle. While defining the portfolio, you wanted to make a preliminary screening of the proposed components in order to filter them based on the acceptance criteria. Which of the following techniques you use?
Correct Answer:
C
You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The portfolio roadmap is used abundantly as an input to 7 processes. When it comes to managing portfolio value, how is the portfolio roadmap used?
Correct Answer:
A