QUESTION 96

Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. When it comes to managing portfolio risks, which of the following activities is used

Correct Answer: B

QUESTION 97

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. What you use to perform this?

Correct Answer: D

QUESTION 98

You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The Portfolio Roadmap is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Roadmap purpose and focus?

Correct Answer: A

QUESTION 99

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. Which of the below helps in optimizing the supply and demand?

Correct Answer: B

QUESTION 100

Assume you are a member of your company's Portfolio Review Board. Your Board meets quarterly to determine which new components to undertake and selects them even if it means the portfolio then will require rebalancing. As you consider the proposed business case for a component and assess the suggestions of the other Board members, a key factor is:

Correct Answer: B