You are managing a large construction portfolio. Recently, and due to budget cuts, you have been having resources issues on multiple initiatives and has been struggling with maintaining a healthy resource allocations. You are currently analyzing the capability and capacity for scarce machinery resources shared across three major programs in the portfolio. What are you currently applying?
Correct Answer:
A
As part of the periodical strategic management cycle, the portfolio management team is revising the portfolio and re-doing the strategic management part. Currently, they are assuming and evaluating different combinations of components in order to come up with multiple approaches and take a decision on the portfolio structure. What is currently being performed?
Correct Answer:
B
Assume at this point as the portfolio manager in your mattress company, you are activating portfolio components, updating portfolio reports, and documenting the decisions made at the recent Portfolio Governance Committee meeting as the company moves into new markets. You are therefore:
Correct Answer:
D
You have scored the portfolio components and are analyzing the data in order to prioritize the components. Using the following scoring table, which of the options represents the correct Components Priority?
Larger image
Correct Answer:
D
One of your component managers has submitted his resignation and left the company; a new program manager joins the portfolio replacing him. Which document you use to inform the new program manager about his responsibilities in the portfolio?
Correct Answer:
C