00:00

QUESTION 21

Which of the following is required in Scrum?

Correct Answer: A

QUESTION 22

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The Development Team is unsure if the required velocity is achievable.
What is the most effective way to recover?

Correct Answer: B
Scrum is founded on empirical process control and asserts that knowledge comes from experience and making decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and control risk. At the end of every Sprint, an increment of ‘done’ work must be available in order to inspect and adapt accordingly.

QUESTION 23

A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing.
What three scenarios has likely occurred? (Choose three.)

Correct Answer: ABC
At the end of a Sprint, the new Increment must be ‘Done’, which means it must be in useable condition and meet the Scrum Team’s Definition of Done.

QUESTION 24

What would be the responsibilities of a self-organizing Development Team?

Correct Answer: B

QUESTION 25

What would be good ways of creating Development Teams that would support the Scrum values?

Correct Answer: B
The ones that will be doing the work are the best ones to decide on what Development Team structures work best.