- (Exam Topic 2)
Which role is responsible for appointing the senior user in a project that is independent from a program?
Correct Answer:
C
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/
- (Exam Topic 2)
Which theme verifies that a project's products are fit for purpose?
Correct Answer:
C
Reference
http://prince2.wiki/Quality
- (Exam Topic 2)
Which is a responsibility of a risk owner?
Correct Answer:
C
- (Exam Topic 2)
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
Correct Answer:
B
- (Exam Topic 1)
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Correct Answer:
B