QUESTION 11

- (Exam Topic 1)
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Correct Answer: B

QUESTION 12

- (Exam Topic 2)
Which theme estimates the cost of delivering the project?

Correct Answer: A

Reference
http://prince2.wiki/Business_Case

QUESTION 13

- (Exam Topic 2)
According to the 'tailor to suit the project' principle, what is the basis for effective project management?

Correct Answer: D

Reference
http://prince2.wiki/Tailor_to_suit_the_project_environment

QUESTION 14

- (Exam Topic 2)
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

Correct Answer: C

QUESTION 15

- (Exam Topic 1)
Which process covers the work done by external suppliers who may NOT be using PRINCE2?