QUESTION 71

- (Exam Topic 2)
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Correct Answer: B

QUESTION 72

- (Exam Topic 2)
Which of the following statements about lines of authority and reporting are true?
* 1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
* 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

Correct Answer: C

QUESTION 73

- (Exam Topic 2)
Which is a purpose of a Risk Register?

Correct Answer: A

QUESTION 74

- (Exam Topic 2)
Which is a purpose of the Managing a Stage Boundary process?

Correct Answer: A

QUESTION 75

- (Exam Topic 2)
Which is a true statement about acceptance criteria?

Correct Answer: D