QUESTION 61

- (Exam Topic 2)
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

Correct Answer: B

QUESTION 62

- (Exam Topic 2)
Which risk response type is appropriate to respond to an opportunity?

Correct Answer: C

QUESTION 63

- (Exam Topic 1)
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Correct Answer: B

QUESTION 64

- (Exam Topic 2)
How does the project board use the 'manage by stages' principle to control the project?

Correct Answer: B

Reference
http://prince2.wiki/Manage_by_stages

QUESTION 65

- (Exam Topic 2)
What information should be recorded in the quality register?

Correct Answer: C
Reference https://mplaza.pm/prince2-quality-register-template/