- (Exam Topic 2)
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
Correct Answer:
B
- (Exam Topic 2)
Which risk response type is appropriate to respond to an opportunity?
Correct Answer:
C
- (Exam Topic 1)
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Correct Answer:
B
- (Exam Topic 2)
How does the project board use the 'manage by stages' principle to control the project?
Correct Answer:
B
Reference
http://prince2.wiki/Manage_by_stages
- (Exam Topic 2)
What information should be recorded in the quality register?
Correct Answer:
C
Reference https://mplaza.pm/prince2-quality-register-template/