- (Exam Topic 2)
Which is a purpose of the Risk Register?
Correct Answer:
B
- (Exam Topic 2)
Which control must be used as a minimum requirement for applying the 'progress' theme?
Correct Answer:
B
- (Exam Topic 2)
Which is an objective of the 'directing a project' process?
Correct Answer:
B
Reference
http://prince2.wiki/Directing_a_Project#Objective
- (Exam Topic 2)
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Correct Answer:
A
- (Exam Topic 2)
Which is a purpose of the Risk theme?
Correct Answer: