QUESTION 56

- (Exam Topic 2)
Which is a purpose of the Risk Register?

Correct Answer: B

QUESTION 57

- (Exam Topic 2)
Which control must be used as a minimum requirement for applying the 'progress' theme?

Correct Answer: B

QUESTION 58

- (Exam Topic 2)
Which is an objective of the 'directing a project' process?

Correct Answer: B
Reference
http://prince2.wiki/Directing_a_Project#Objective

QUESTION 59

- (Exam Topic 2)
What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Correct Answer: A

QUESTION 60

- (Exam Topic 2)
Which is a purpose of the Risk theme?

Correct Answer: D