- (Exam Topic 1)
Which characteristic distinguishes a project from regular business operations?
Correct Answer:
B
- (Exam Topic 1)
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Correct Answer:
C
- (Exam Topic 2)
The application of which principle helps to define what should be included in a project?
Correct Answer:
C
- (Exam Topic 1)
Which statement about the Directing a Project process is true?
Correct Answer:
A
- (Exam Topic 1)
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
Correct Answer:
B