00:00

QUESTION 51

- (Exam Topic 1)
Which characteristic distinguishes a project from regular business operations?

Correct Answer: B

QUESTION 52

- (Exam Topic 1)
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Correct Answer: C

QUESTION 53

- (Exam Topic 2)
The application of which principle helps to define what should be included in a project?

Correct Answer: C

QUESTION 54

- (Exam Topic 1)
Which statement about the Directing a Project process is true?

Correct Answer: A

QUESTION 55

- (Exam Topic 1)
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

Correct Answer: B