- (Exam Topic 2)
What is established during the 'initiating a project' process?
Correct Answer:
A
- (Exam Topic 2)
Which is shown in a product breakdown structure?
Correct Answer:
C
- (Exam Topic 2)
Which of the following statements about customer's quality expectations and acceptance criteria are true?
* 1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
* 2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
Correct Answer:
D
- (Exam Topic 2)
Which is a purpose of the quality theme?
Correct Answer:
A
- (Exam Topic 2)
Which role represents the stakeholders who will operate the project's products after the project is complete?
Correct Answer:
B
Reference