00:00

QUESTION 36

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Correct Answer: C
The project risks are documented in the risk register - including the probability and impact information. The risk register is an output of the Identify Risks process. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis,
and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register.
Answer option A is incorrect. The risk management plan addresses that how risks will be identified, monitored, and controlled.
Answer option D is incorrect. The activity attributes information is needed, but risks are not part of the activity attributes.
Answer option B is incorrect. The schedule management plan addresses how the schedule will be created, executed, and controlled.

QUESTION 37

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Correct Answer: BCD
Constructability analysis takes into account the location, logistics, resource availability analysis, the average price of general labor in the area, and labor productivity studies from previous similar projects in the area. Constructability analysis is a process that starts in the initial planning phases and persists all over the entire planning cycle and into the implementation phase of the project. Constructability analysis during the planning process examines the methods and cost of installed equipment and materials, technology, site conditions, resources, and related infrastructure. The benefit of constructability analysis is to reduce both the time and cost of a project. Constructability analysis is repeatedly performed throughout the life-cycle of a project in order to optimize cost, plan, and schedule while mitigating risk. It is a very important process that needs to be performed early in planning to allow alternatives to be considered and integrated into the design. Answer option A is incorrect. This comes under the quality assurance phase.

QUESTION 38

Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

Correct Answer: ABC
The characteristics of conflict and the conflict management process recognized by the project managers while handling conflict in a team environment are as follows: Conflict is natural and forces a search for alternatives. Openness resolves conflict. Conflict resolution should focus on issues, not personalities. Conflict is a team issue. Conflict resolution should focus on the present, not the past.

QUESTION 39

Mark works as a project manager for BlueWell Inc. He is making relevant information available to the project stakeholders as required. According to Mark, which of the following
are NOT the tools and techniques of the Distribute Information process?

Correct Answer: AD
These tools and techniques are used in the Plan communications process. The tools and techniques used in the Distribute information process are as follows: Communication methods: These methods includes individual and group meetings, computer chats, audio and video conferences and other remote communications methods to distribute information. Information distribution tools: Various information distribution tools can be used to distribute information such as electronic tools, electronic conferencing tools, hard copy document distribution etc.

QUESTION 40

Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?

Correct Answer: D
When Holly adds resources to the project, as in this instance, she will need to update the activity attributes to reflect the new labor. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. In project document updates, activity attributes are updated to include any revised resource requirements and other revision generated by the develop schedule process.