00:00

QUESTION 71

In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

Correct Answer: C
Of all six processes, the control schedule process will take the majority of the time in the project time management knowledge area. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process.
Answer options B, A, and D are incorrect. These processes will not take the longest to complete.

QUESTION 72

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

Correct Answer: C
The integrated change control process reviews proposed changes and determines what effect the change will have on the entire project. This includes scope, time, cost, quality, human resources, communication, risk, and procurement. Integrated change control is a way to manage the changes incurred during a project. It is a method that manages reviewing the suggestions for changes and utilizing the tools and techniques to evaluate whether the change should be approved or rejected. Integrated change control is a primary component of the project's change control system that examines the affect of a proposed change on the entire project.
Answer option A is incorrect. Scope change control focuses only on the effect of the change on the project scope.
Answer option B is incorrect. Schedule change control focuses only on the effect of the change on the schedule.
Answer option D is incorrect. The Change Control Board is a committee of key stakeholders, usually management, the project manager, and the project customer, to evaluate proposed changes. This board, however, is not a project process.

QUESTION 73

Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

Correct Answer: C
The best answer for this question is a template. When projects adapt previous project plans for the current project, it is an example of a project template. Template is an activity list or a part of the activity list taken from the previous project and used in a new project.
Answer option D is incorrect. A parametric estimate is an estimate that uses a parameter to predict the costs of the project, such as cost per network drop or cost per software license. Parametric estimating technique utilizes the statistical relationship that exists between a series of historical data and a particular delineated list of other variables.
Answer option A is incorrect. Expert judgment is not the best choice for this question. Expert judgment is a technique based on a set of criteria that has been acquired in a specific knowledge area or product area. It is obtained when the project manager or project team requires specialized knowledge that they do not possess. Expert judgment involves people most familiar with the work of creating estimates. Preferably, the project team member who will be doing the task should complete the estimates. Expert judgment is applied when performing administrative closure activities, and experts should ensure the project or phase closure is performed to the appropriate standards.
Answer option B is incorrect. Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimation of the same parameter for a future activity. It is a top-down estimating technique and is a form of expert judgment. It provides a lower degree of accuracy than other estimating techniques.
This technique is primarily used when there is a limited amount of detailed information about the project or program.

QUESTION 74

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

Correct Answer: D
The schedule baseline is a required component of the project management plan. Project management plan is a formal, agreed document that defines how the project is executed, monitored and controlled. It may be summary or detailed and may be composed of one or more subsidiary management plans and other planning documents. The objective of a project management plan is to define the approach to be used by the project team to deliver the intended project management scope of the project. The project manager creates the project management plan with the inputs from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders.
Answer option C is incorrect. The schedule baseline is not a project objective.
Answer option A is incorrect. The project calendar defines when the project will take place. Answer option B is incorrect. Project constraints are restrictions imposed on the project, such as time, cost, and scope.

QUESTION 75

Della works as a Project Manager for BlueWell Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?

Correct Answer: A
According to the question, the schedule variance (SV) of the project is zero. A value of 0 indicates that the project is right on target. Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.
Answer option C is incorrect. The negative SV means that project is behind the schedule. Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the project.
Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned schedule.