Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:
Correct Answer:
C
A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.
Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that those issues are resolved?
Correct Answer:
C
The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?
Correct Answer:
B
A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations. Which approach will better cope with the
requirements' volatility?
Correct Answer:
B
A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible. Which activity should the business analyst initiate before beginning requirements elicitation?
Correct Answer:
A