QUESTION 46

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example,Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?

Correct Answer: D

QUESTION 47

What should the business analyst do during the first steps of a project?

Correct Answer: B

QUESTION 48

The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.
Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid recommendation"?

Correct Answer: D

QUESTION 49

What is one benefit of documenting the change control process?

Correct Answer: C

QUESTION 50

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met. What could have caused this issue?

Correct Answer: B