00:00

QUESTION 41

An agile team member identifies a potential problem within the project team How should the team's coach react?

Correct Answer: C

QUESTION 42

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Correct Answer: C

QUESTION 43

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

Correct Answer: B

QUESTION 44

A project is starling and the type of wont is complex and suitable for agile in assessing the learn members it appears that co-location would be a challenge.
What should the agile practitioner do?

Correct Answer: A

QUESTION 45

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.
What should the project leader do?

Correct Answer: A