An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?
Correct Answer:
C
A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?
Correct Answer:
B
A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup.
What should the Scrum Master do?
Correct Answer:
A
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?
Correct Answer:
C
An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.
What should the team do?
Correct Answer:
C