00:00

QUESTION 26

Agile team A struggles to deliver committed stories due to technical dependencies with team B, which continuously fails to meet its delivery commitments. What should the agile team lead do?

Correct Answer: B

QUESTION 27

During sprint planning the product owner wants the team to prioritize and deliver a number of features which nave the highest business value Due to technical dependencies the team does not agree with the prioritization What should the project leader do'

Correct Answer: C

QUESTION 28

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient.
What should the project team have done prior to product release?

Correct Answer: D

QUESTION 29

During a planning session, four out of five team members vole to include eight story points m a particular story, while the fifth member votes for five story points How should this be handled7

Correct Answer: C

QUESTION 30

A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate.
What should the agile project leader do?

Correct Answer: C