QUESTION 26

A product owner asks a newly formed scrum team how many story points will be completed m a sprint What should the scrum master do?

Correct Answer: A

QUESTION 27

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

Correct Answer: C

QUESTION 28

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

Correct Answer: A

QUESTION 29

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
What should the project leader do?

Correct Answer: C

QUESTION 30

During a retrospective the agile practitioner discovers that a team member's process improvement idea has worsened the outcome What should the agile practitioner do?