QUESTION 16

What should the agile practitioner know about tracking velocity?

Correct Answer: C

QUESTION 17

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments. What should the agile coach do?

Correct Answer: C

QUESTION 18

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?

Correct Answer: B

QUESTION 19

The customer needs assistance m determining the efficiency of a set of process activities within the solution. What should the agile team do?

Correct Answer: D

QUESTION 20

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do?

Correct Answer: B