An organization highly values security However, a team member on a project has found a way to save time and money with less robust security features. What should the team member do?
Correct Answer:
D
A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists is impacting team velocity.
What should the agile team lead do?
Correct Answer:
B
A product owner new to the role is very enthusiastic about an agile protect with an energetic team. What should be done first to ensure successful delivery of the product?
Correct Answer:
A
A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
Correct Answer:
B
The learn is refining user stones during the backlog grooming session and confused on the acceptance criteria and level of details What should the agile practitioner do?
Correct Answer:
C