00:00

QUESTION 36

- (Topic 1)
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Correct Answer: B

QUESTION 37

- (Topic 4)
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Correct Answer: B

QUESTION 38

- (Topic 1)
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Correct Answer: A

QUESTION 39

- (Topic 4)
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Correct Answer: A

QUESTION 40

- (Topic 4)
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Correct Answer: C