00:00

QUESTION 31

- (Topic 4)
Which of the following documents allows the project manager to assess risks that may require near term action?

Correct Answer: C

QUESTION 32

- (Topic 2)
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Correct Answer: C

QUESTION 33

- (Topic 2)
The following is a network diagram for a project.
PMI-100 dumps exhibit
The shortest non-critical path for the project is how many days in duration?

Correct Answer: A

QUESTION 34

- (Topic 1)
Which Control Quality tool is also known as an arrow diagram?

Correct Answer: D

QUESTION 35

- (Topic 1)
A technique used to determine the cause and degree of difference between baseline and actual performance is:

Correct Answer: B