00:00

QUESTION 116

- (Topic 3)
The links between the processes in the Process Groups are often:

Correct Answer: B

QUESTION 117

- (Topic 4)
Which of the following is an input to Develop Human Resource Plan?

Correct Answer: D

QUESTION 118

- (Topic 4)
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Correct Answer: C

QUESTION 119

- (Topic 5)
After Define Activities and Sequence Activities, the next process is:

Correct Answer: A

QUESTION 120

- (Topic 2)
The following is a network diagram for a project.
PMI-100 dumps exhibit
What is the critical path for the project?

Correct Answer: A