- (Topic 3)
The links between the processes in the Process Groups are often:
Correct Answer:
B
- (Topic 4)
Which of the following is an input to Develop Human Resource Plan?
Correct Answer:
D
- (Topic 4)
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
Correct Answer:
C
- (Topic 5)
After Define Activities and Sequence Activities, the next process is:
Correct Answer:
A
- (Topic 2)
The following is a network diagram for a project.
What is the critical path for the project?
Correct Answer:
A