- (Topic 2)
An input to the Control Quality process is:
Correct Answer:
D
- (Topic 2)
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
Correct Answer:
A
- (Topic 1)
An output of the Create WBS process is:
Correct Answer:
A
- (Topic 2)
The zero duration of milestones in project planning occurs because milestones:
Correct Answer:
C
- (Topic 4)
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Correct Answer:
A