- (Topic 2)
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
Correct Answer:
B
- (Topic 4)
Which of the following Project Communication Management processes uses performance reports as an input?
Correct Answer:
C
- (Topic 4)
Project contracts generally fall into which of the following three broad categories?
Correct Answer:
A
- (Topic 4)
Which of the following reduces the probability of potential consequences of project risk events?
Correct Answer:
A
- (Topic 4)
Which technique helps to determine the risks that have the most potential impact on a project?
Correct Answer:
D