- (Topic 5)
Which is an output of the Collect Requirements process?
Correct Answer:
A
- (Topic 4)
Which of the following are outputs of Develop Project Team?
Correct Answer:
D
- (Topic 1)
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Correct Answer:
B
- (Topic 5)
Which of the following is a project constraint?
Correct Answer:
D
- (Topic 2)
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
Correct Answer:
B