Which process determines the risks that might affect the project?
Correct Answer:
B
- (Topic 1)
Which process determines the risks that may affect the project and documents their characteristics?
Correct Answer:
D
- (Topic 1)
Enterprise environmental factors are an input to which process?
Correct Answer:
C
- (Topic 2)
In the Define Activities process, the schedule management plan is used to:
Correct Answer:
D
- (Topic 1)
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
Correct Answer:
D