QUESTION 76

- (Topic 3)
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Correct Answer: D

QUESTION 77

- (Topic 1)
A project charter is an output of which Process Group?

Correct Answer: C

QUESTION 78

- (Topic 4)
"Tailoring" is defined as the:

Correct Answer: A

QUESTION 79

- (Topic 4)
When large or complex projects are separated into distinct phases or subprojects, all of the
Process Groups would normally be:

Correct Answer: B

QUESTION 80

- (Topic 2)
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?