- (Topic 3)
Which of the following investigates the likelihood that each specific risk will occur?
Correct Answer:
D
- (Topic 3)
Which defines the portion of work included in a contract for items being purchased or acquired?
Correct Answer:
D
- (Topic 2)
During which process does the project team receive bids and proposals?
Correct Answer:
A
- (Topic 1)
Which input to the Plan Risk Management process provides information on high-level risks?
Correct Answer:
A
- (Topic 3)
An input of the Plan Procurement Management process is:
Correct Answer:
B