QUESTION 41

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Correct Answer: D

QUESTION 42

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Correct Answer: C

QUESTION 43

The progressive detailing of the project management plan is called:

Correct Answer: B

QUESTION 44

Which items are components of a project management plan?

Correct Answer: A

QUESTION 45

The number of potential communication channels for a project with 5 stakeholders is:

Correct Answer: A