QUESTION 21

The process of identifying and documenting relationships among the project activities is known as:

Correct Answer: B

QUESTION 22

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Correct Answer: B

QUESTION 23

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Correct Answer: A

QUESTION 24

Which schedule development tool and technique produces a theoretical early start date and late start date?

Correct Answer: A

QUESTION 25

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Correct Answer: A