00:00

QUESTION 76

An example of a group decision-ma king technique is:

Correct Answer: B

QUESTION 77

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Correct Answer: B

QUESTION 78

A tool or technique used in the Control Procurements process is:

Correct Answer: B

QUESTION 79

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Correct Answer: A

QUESTION 80

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Correct Answer: A