- (Exam Topic 21)
Maintenance testing is:
Correct Answer:
B
- (Exam Topic 21)
Which of the following is most likely to cause failure in the implementation of a test tool?
Correct Answer:
C
- (Exam Topic 22)
Refer to the exhibit
The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window
The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests.
Which of the following gives an appropriate test execution schedule, taking account of the prioritisation and other constraints? [K3]
Correct Answer:
C
- (Exam Topic 18)
Why might a RAD approach be a better option for the test manager rather than a sequential development? 2 credits
Correct Answer:
B
- (Exam Topic 15)
Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)
Correct Answer:
CDE