QUESTION 31

- (Exam Topic 3)
During which stage of the fundamental test process is the testability of requirements evaluated?

Correct Answer: D

QUESTION 32

- (Exam Topic 3)
Which of the following type of defect would NOT be typically found by using a static analysis tool?

Correct Answer: C

QUESTION 33

- (Exam Topic 1)
Which of the following is a correct set of boundary values to test the "Group Size" parameter, as defined by the following statement;
"In a reservation system for groups visiting a small museum, the graphical user interface presents a field asking the number of group members. Group size can be anywhere from 2 to 20 visitors"

Correct Answer: C

QUESTION 34

- (Exam Topic 3)
Which of the following statements about static analysis are FALSE?

Correct Answer: C

QUESTION 35

- (Exam Topic 2)
What factors should be considered to determine whether enough testing has been performed? (i)The exit criteria.
(ii) The budget.
(iii) How big the test team is. (iv)The product's risk profile. (v)How good the testing tools are.
(vi) Sufficient details of the system status to allow decisions

Correct Answer: A