- (Exam Topic 9)
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
* a. Any deviation from the procedures described in the test
* b. strategy document
* c. The overall estimated costs, timescales and resource
* d. requirements
* e. A detailed schedule of testing activities
* f. The development deliverables to be tested
* g. Which test staff members (names) will be involved and when
* h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Correct Answer:
CE
- (Exam Topic 13)
Important consequences of the impossibility of complete testing are:
Correct Answer:
D
- (Exam Topic 13)
A top-down development strategy affects which level of testing most?
Correct Answer:
B
The development strategy will affect the component testing (option (A)), in so far as it cannot be tested unless it has been built. Options (C) and (D) require the system to have been delivered; at these points the development strategy followed is not important to the tester. Option (B) needs knowledge of the development strategy in order to determine the order in which components will be integrated and tested.
- (Exam Topic 7)
In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons. 1 credit
Correct Answer:
ADE
- (Exam Topic 10)
The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage? 2 credits
Correct Answer:
A