Which of the following would you expect to see in the master test plan? 1 credit
Correct Answer:
C
Which of the following would be appropriate test objectives for user acceptance testing of the first release of a new software product aimed at a general market and built using Agile methods? [K2]
Correct Answer:
D
Under which of the following circumstances is maintenance testing required? [K1]
Correct Answer:
A
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
Correct Answer:
CE
Which of the following accurately defines the integration testing test level? [K2]
Correct Answer:
A