QUESTION 11

Which of these is Discrete data?

Correct Answer: C

QUESTION 12

The reported Cpk for a process with an average of 94 units, a spread of 22 units and upper and lower specification limits of 125 and 80 units would be?

Correct Answer: B

QUESTION 13

A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data: Cutting38 Forming17 Stitching56 Sealing42

Correct Answer: C

QUESTION 14

One of the metrics commonly used in Lean Six Sigma is DPU. This acronym stands for __________.

Correct Answer: B

QUESTION 15

A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.

Correct Answer: A