- (Topic 2)
Yolanda is the web designer for your company and you are the business analyst. You are working with Yolanda on a new website that your company will host. You'd like for her to create a mock-up of the website without spending much time on the actual workings behind the web interface. You'd like for her to show the customer how the website will look, some idea of the functionality of the website, and some basic graphics and colors so the customer can see the direction of the project.
What type of prototype are you asking Yolanda to create?
Correct Answer:
D
- (Topic 3)
Which of the following captures all of the activities within a business, the inputs and outputs of each activity, and the required resources to complete each activity?
Correct Answer:
B
- (Topic 3)
Which of the following is the formal acceptance of the project?
Correct Answer:
B
- (Topic 3)
Which of the following defines how the project scope should be created, executed, monitored and controlled, and then validated?
Correct Answer:
B
- (Topic 1)
You are the business analyst for your organization and are working with Jennifer to conduct stakeholder analysis. You would like to create a RACI chart to help with the roles of the people involved in the stakeholder analysis process. Jennifer is not familiar with this chart and asks what does RACI mean. Which one of the following best describes the RACI chart in the conduct stakeholder analysis process?
Correct Answer:
A