- (Topic 1)
What plan includes the description of the scope of work, the deliverable Work
BreakdownStructure, the activity list, and estimates for the business analysis activities?
Correct Answer:
D
- (Topic 2)
Enterprise analysis provides many things for an organization. All of the following are tasks included in enterprise analysis except for which one?
Correct Answer:
D
- (Topic 2)
You have completed the requirements documentation and the stakeholders have signed off on the requirements. Now the requirements are advancing into a project as your organization has chartered a project based on the identified requirements. What stakeholder is now responsible for assessing the solution scope to determine the project scope?
Correct Answer:
B
- (Topic 2)
The creative thinking process has three values to determine the effectiveness of the process.
Which one of the following is not a measurement of effective creative thinking?
Correct Answer:
B
- (Topic 3)
Which of the following is a procurement document?
Correct Answer:
D