- (Exam Topic 6)
Why is tailoring in a project necessary?
Correct Answer:
D
Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
- (Exam Topic 4)
In which Project Management Process Group is the project charter developed?
Correct Answer:
C
- (Exam Topic 4)
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
Correct Answer:
C
- (Exam Topic 3)
What cost control technique is used to compare actual project performance to planned or expected performance?
Correct Answer:
D
- (Exam Topic 1)
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Correct Answer:
C