00:00

QUESTION 16

- (Exam Topic 6)
Under which circumstances should multiple projects be grouped in a program?

Correct Answer: A

QUESTION 17

- (Exam Topic 2)
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Correct Answer: A

QUESTION 18

- (Exam Topic 1)
The ability to influence cost is greatest during which stages of the project?

Correct Answer: A

QUESTION 19

- (Exam Topic 1)
An output of the Plan Quality Management process is:

Correct Answer: A

QUESTION 20

- (Exam Topic 6)
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Correct Answer: D