QUESTION 11

- (Exam Topic 4)
Which activity involves ensuring that the composition of a projects configuration items is correct?

Correct Answer: C

QUESTION 12

- (Exam Topic 3)
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Correct Answer: B

QUESTION 13

- (Exam Topic 4)
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Correct Answer: D

QUESTION 14

- (Exam Topic 6)
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

Correct Answer: C

QUESTION 15

- (Exam Topic 6)
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

Correct Answer: D