00:00

QUESTION 11

- (Exam Topic 2)
Which type of organizational structure is displayed in the diagram provided?
CAPM dumps exhibit

Correct Answer: B

QUESTION 12

- (Exam Topic 3)
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Correct Answer: C

QUESTION 13

- (Exam Topic 4)
Which of the following documents allows the project manager to assess risks that may require near term action?

Correct Answer: C

QUESTION 14

- (Exam Topic 1)
Which Process Group and Knowledge Area include the Sequence Activities process?

Correct Answer: C

QUESTION 15

- (Exam Topic 3)
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Correct Answer: A