00:00

QUESTION 86

- (Exam Topic 5)
An input to the Collect Requirements process is the:

Correct Answer: A

QUESTION 87

- (Exam Topic 2)
Which stakeholder approves a project's result?

Correct Answer: A

QUESTION 88

- (Exam Topic 4)
Which characteristic do projects and operational work share in common?

Correct Answer: B

QUESTION 89

- (Exam Topic 2)
In complex projects/ initiating processes should be completed:

Correct Answer: B

QUESTION 90

- (Exam Topic 6)
Which statement about identification and engagement of stakeholders during a project is correct?

Correct Answer: A