QUESTION 81

- (Exam Topic 5)
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Correct Answer: C

QUESTION 82

- (Exam Topic 4)
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Correct Answer: D

QUESTION 83

- (Exam Topic 2)
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Correct Answer: C

QUESTION 84

- (Exam Topic 5)
The cost benefit analysis tool is used for creating:

Correct Answer: B

QUESTION 85

- (Exam Topic 1)
Inputs to the Plan Schedule Management process include:

Correct Answer: A