QUESTION 51

- (Exam Topic 3)
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Correct Answer: C

QUESTION 52

- (Exam Topic 1)
An input to the Identify Stakeholders process is:

Correct Answer: C

QUESTION 53

- (Exam Topic 4)
Project contracts generally fall into which of the following three broad categories?

Correct Answer: A

QUESTION 54

- (Exam Topic 5)
Risk exists the moment that a project is:

Correct Answer: B

QUESTION 55

- (Exam Topic 4)
Which of the following is an input to the Direct and Manage Project Execution process?

Correct Answer: A